Williamsport, PA

Design and Construction Inspection for the Hepburn Trailhead

This project included the Design and Construction Inspection of the new access road for the Hepburn Street Pump Station and Riverwalk Parking Area. Major components included the new entrance off the I-180 Exit Ramp, new roadway connection to the Hepburn Street Pump Station, new Railroad Crossing and Signal, new Riverwalk Parking Area, stormwater drainage, fencing, gates and signage. The new parking area provides 91 parking stalls and trash cans for the Riverwalk.

Design activities included the entire site design, E&S, Highway Occupancy Permit and Railroad Coordination.

Construction Services included Inspection and Construction Management including daily observation & documentation, change orders, pay applications, Railroad Coordination and HOP Coordination.

Ready to discuss your project?