Rose Tree Media School District Delaware County, PA

School District CNG Feasibility Study – Rose Tree Media

Rose Tree Media School District had a need for a time-fill and fast-fill fueling operation. Larson Design Group, in collaboration with Small Arrow Engineering, prepared a feasibility report including a site plan of the proposed design. The site plan indicated all existing utilities, proposed new gas and electric distribution lines, and provided details of the time-fill posts and two fast-fill locations.

The maintenance repair garage was investigated to determine modifications required to be CNG compliant. It was observed that electrical conduit and motors in the 18″ Class 1, Div 2 will need to be moved out of the 18″. The heating equipment will need to be replaced with a make-up air heater or infrared radiant heater. Methane detection was recommended in lieu of continuous ventilation.